2516 T-beams have been built in Danzao beam making

2022-08-08
  • Detail

2516 pieces of T-beams have been made in the Danzao beam making yard of Guangzhou Zhuhai railway, and the erection of beams is expected to be completed by the end of the month.

2516 pieces of T-beams have been made in the Danzao beam making yard of Guangzhou Zhuhai railway, and the erection of beams is expected to be completed by the end of the month.

China Construction machinery information

Guide: at 23:30 on April 7, with the last bucket of concrete successfully put into the mold, the last piece of precast T-beams in the Danzao beam making yard of Guangzhou Zhuhai railway was cast and formed, reaching the node construction period goal that the owner first requires high metal strength, It is expected to complete the beam erection task by the end of this month. Danzao selected 3 minimum diameter beam making fields measured, located in Danzao Town, Nanhai District, Foshan City, Guangdong Province, by

at 23:30 on April 7, with the last bucket of concrete successfully put into the mold, the last piece of precast T-beam in Danzao Beam Yard of Guangzhou Zhuhai railway was cast and formed, which reached the node construction period target required by the owner, and it is expected to complete the beam erection task by the end of this month

Located in Danzao Town, Nanhai District, Foshan City, Guangdong Province, the Danzao beam fabrication yard is constructed by the second company of China Railway Construction 25th bureau group, which is responsible for the prefabrication and erection of 2516 simply supported T-beams for 14 double track bridges from Beijiang super major bridge to Xijiang super major bridge section (main line) of Guangzhou Zhuhai railway

Wang Gang, deputy chief engineer, said that as of April 8, the erection of Danzao beam manufacturing plant had been completed, 2364 T-beams must be installed on the safety device, and there are 152 beams in the beam field. "According to the current construction progress of 12 beams per day, we can complete the erection of the remaining beams by the end of April." Wang Gang said

in 2011, due to the impact of domestic and foreign economic situation, the construction funds of Danzao beam manufacturing plant were increasingly tight, and the construction was suspended in October last year. However, in order to fulfill the contract in good faith and meet the owner's construction period requirements, the construction was resumed in February this year

in order to complete the prefabrication and erection of T-beams as soon as possible, the beam yard should make overall plans and reasonably deploy human, material and financial resources. The research team of Liangchang workers has begun to test new derivatives of composite materials. They are fighting wits and braves with time and weather, working in sunny days, rainy days, lighting at night, and working overtime on holidays. With the hard work of "white plus black, five plus two", they are working hard towards the expected goal of opening the Guangzhou Zhuhai railway in October this year

Danzao beam manufacturing plant entered the site in early December 2009, always adhering to the standards of high standards, strict requirements and scientific construction. It has created a series of records such as prefabricating the first beam 100 days after entering the site, passing the national industrial product production license certification at one time after careful preparation for 4 months, and starting T-beam erection one month after certification